Karnataka Achieves 85 Percent Progress in Railway Electrification

Karnataka Achieves 85.11 % and SWR 85 % Progress in Railway Electrification as on 31.12.2023

- Advertisement -

Overview

Karnataka has marked a notable milestone with 85.11% of its railway routes electrified as of December 31, 2023. The South Western Railway(SWR), serving the state, stands at an impressive 85% electrification rate.

National Electrification Status

The Indian Railways reports a nationwide electrification rate of 93.83% as of December 31, 2023. The electrified broad gauge (BG) route spans 61,508 RKM (Route Kilometers), with 4,048 RKM currently undergoing electrification.

Also read | SWR Initiates Electrification Surveys for New Lines

- Advertisement -

State-Wise Achievements

Karnataka secures the 25th position among states with its 85.11% electrified network. Other top-performing states include Chandigarh, Chhattisgarh, Delhi, Haryana, and Himachal Pradesh, each boasting 100% electrification.

Railway Electrification - State-Wise and Zone wise Achievements

Also read | Railways to conduct Electrification Survey between Vyasa Colony & Amravathi Colony

Zone-Wise Progress

Among railway zones, South Western Railway stands at 85%, contributing to the overall success. Leading zones with 100% electrification include NCR, ECOR, NER, WCR, CR, ER, KRCL, Metro, SECR, and SER.

- Advertisement -
Railway Electrification - State-Wise and Zone wise Achievements

Also read | India’s First Vande Bharat Sleeper Trainset Prototype under production at BEML Bengaluru 

Pending Electrification in Karnataka

While Karnataka celebrates its achievement, some routes still await electrification, including Vyasa Colony – Amaravathi Colony, Taj Sultanpur – Khanapur, Hole Narasipur – Hassan, Sakaleshpur – Kabaka Puttur, Suldhal – Ghataprabha, Kudachi – Miraj, and Wandal – Bagalkot. The Mysuru – Chamarajanagar line is nearly complete, with only a 900-meter stretch pending due to a pending NOC from AAI for OHE installation near Mysuru Airport.

Also read | SWR Speeds Up Bengaluru – Belagavi Superfast Express

- Advertisement -

Budget and Future Plans

The Budget Outlay for Railway Electrification in 2023-24 is set at 8,070 Crores, reflecting the commitment to further enhancing the electrification infrastructure.

In conclusion, Karnataka’s progress in railway electrification is commendable, contributing to the nationwide goal of a more sustainable and efficient rail network.

Also read | Powering the Rails: Karnataka Surges with 74% Railway Route Electrification!

- Advertisement -
RELATED ARTICLES

Leave a Reply

- Advertisment -

Most Popular

Discover more from Mysuru Infra Hub

Subscribe now to keep reading and get access to the full archive.

Continue reading