Railways have invited bids for the construction of a new BG line between Lokapur(Excl) Yadwad(incl) from KM 39/000 to 60/000(21 KM) in the Bagalkot -Kudachi new rail line project on EPC Mode. The works shall also include Signalling & Telecommunication works and General Electrical services.
Estimated Project Cost – 357.46 cr
Length – 21 KM
No. of Years for completion of works – 24 Months
Features of the proposed railway stations
- Dadanhatti Halt Station @CH: 43.900klm
- Station Building
- 1 Main Line
- 1 High-level Platform of 570M X 6M
- Bommanbudni Crossing Station @CH: 49.300klm
- Station Building
- 1 Main Line
- 2 Loop Lines
- 2 High-level platforms of 570M X 6M
- 1 Subway 1×3.0x3.0M RCC Box with Steps and Ramp
- Yadwad Crossing Station @CH:58.900klm
- Station Building
- 1 Main Line
- 2 Loop Lines (1 Goods Line)
- 1 High-level Platform of 570M X 6M
- 1 Goods Platform of 700M X 20M
- 1 Foot Over Bridge with Steps and Ramp
Kojjidoni – Lokapur section
In December 2021, the state government handed over the required land for the construction of the 9klm Kajjidoni – Lokapur line. Railways have awarded the tender for the same and works have started.