Railways to undertake Construction of an Electrified New BG Line Track between Marikuppam (Incl.) and Dravidian University(5.72 Km) including Telecommunication, Electrification & Electrical works through Engineering, Procurement, and Construction mode. (EPC)
Marikuppam and Dravidian University railway line is a part of the Marikuppam – Kuppam new railway line proposed way back in 2012-13 with an estimated revised cost of Rs.279.54cr for a length of 23.70 Km.
The proposed alignment connects the existing station at Marikuppam on the Bangarpete-Marikuppam branch line and Kuppam on the Bengaluru-Chennai main line. The new line will serve the districts of Kolar in Karnataka and Chittoor in Andhra Pradesh.
Length in km: 5.720klm
Estimated Project Cost: INR 131.542 Crore
Construction Period: 15 months
Features of the proposed stations
- Marikuppam Station
- Station Building
- 1 Main Line
- 2 Loop Lines
- 2 High-Level Platforms 350MX5.5M with provision for future extension
- Foot Over Bridge
- Virupakshpura Halt Station @CH: 4.300klm
- Station Building
- 1 Main Line
- 1 High-Level Platform