The works involve formation of 15m & 18m wide asphalt roads including construction of RCC side drains, culverts and laying of HDPE water pipelines in the industrial estates.
An estimated sum of Rs 16.2 crores will be spent on completing the civil works in Adakanahalli sub layout-2. While the works in Thandya 2nd Stage 1st Phase Industrial Area will cost around Rs. 16.61 crores.
Adakanahalli Industrial Estate is about 538.22 Acres. Industrial usage- 309.7 Acres.
Adakanahalli Industrial Area map. Expected works are to be taken up as marked in the boxed area as that sub layout is yet to be developed.
Thandya phase-II Industrial Estate is about 649.21 Acres.
Thandya phase II Industrial Area map. Expected works are to be taken up as marked in the boxed area as they are yet to be developed.