35 Crore Rail Over Bridge for hassle free movement
Long queues and chaos, a common sight at the Sujathapura railway level crossing will soon be a thing of the past with the proposed Rail Over Bridge (ROB). Increased railway movement has led to severe interruption of vehicular traffic on NH 150A multiple times during the day, especially, affecting the movement of heavy cargo trailers catering to various Industries in the vicinity. Wait gets as long as 15 minutes that often leads to traffic jams. Finally, commuters long-pending demand for a solution has been met with Ministry of Road Transport and Highways (MoRTH) calling a civil tender for the construction of 4 lane ROB and its approaches in lieu of existing Level Crossing No 18 at Km 620 600 on NH 150A at Sujathapuram railway crossing in Nanjangud.
Project Technical Brief


Proposed Superstructure
Superstructure shall comprise of Structural steel girder with RCC deck slab for railway span and precast prestressed concrete girder with RCC deck for viaduct spans. The vertical clearance from Rail top level to the soffit of the steel girder shall be 6.763 M. The superstructure span has a structural skew angle of 20 degrees.

Project Status
The total land required for the project is 8 hectares, of which 6.756 hectares of land needs to be acquired. Land acquisition is progressing with some survey sites listed in 3D Notification while others are in 3A Notification.
A total of 6 bidders submitted their financial quotes and a Hyderabad based firm NSPR Constructions Pvt Ltd has emerged as the lowest bidder L1 with a financial quote of 36.53 crores. The L2 bidder is Krishi Infratech at 37.1 crores. The work shall start as soon as the land is acquired, financial bids are evaluated and the AOC letter is signed.
Stay tuned for more updates..