HomeKarnatakaRailways to construct Hadihalli Belur New Railway Line

Railways to construct Hadihalli Belur New Railway Line

- Advertisement -

Indian Railways has initiated the process for constructing a new 11.60 km Hadihalli Belur New Railway Line under Kadur – Chikkamagaluru – Belur New Line Project Including General Electrical and Electrification Works” on EPC Mode.

  • Length in km: 11.60
  • Estimated Project Cost (In Crores.): 247.501
  • No. of months for completion of work: 18 Months

The project’s proposed alignment is the “Construction of New BG Line for a route length of 11.60 km between Hadihalli and Belur stations,” excluding Hadihalli yard. The objective is to construct a single line with an Absolute Block System, capable of supporting a maximum train speed of 110 km/h, initially accommodating an axle load of 25 tonnes.

The project involves building a new railway line between Chainage 54.880 Km and Chainage 66.480 Km. This includes General Electrical and Electrification Work between Hadihalli and Belur, covering a distance of 11.60 km. The project is part of the Kadur – Chikkamagaluru – Belur New Line Project.

- Advertisement -

The goal of the project is to create a single railway line with an “absolute block system” for trains to travel at a maximum speed of 110 km/h, initially supporting a load of 25 tonnes per axle. The project covers the construction of the track, bridges, and other necessary structures to accommodate this load.

The contract includes the design and construction of civil structures, buildings, electrical systems, signals, telecommunication, and track components for the new railway line. The project encompasses the construction of the following:

  • 5 major bridges, 
  • 21 minor bridges 
  • 3 road under bridges 
  • 6 road over bridges including approaches
Hadihalli Belur New Railway Line
Hadihalli Belur New Railway Line part of Kadur Chikkamagaluru Belur Railway Line

Belur @ Centreline Chainage: 65760

- Advertisement -
  • Station Building with S&T accommodation: 1350 sq.m, Building Floors: Ground + 1, Building Dimensions: 2 x 660 sq.m
  • Number of Lines: 3
  • Number of Platforms: 2
    • PF-1: Length of 570m, High-Level (HL)
    • PF-2: Length of 570m, High-Level (HL)
  • Subway: 1 Nos with one ramp and step on each PF, width of 5m across 3 tracks
  • Subway: 1
  • Watering Line: Length: 550 metres

The Belur railway station is designed with modern amenities to serve passengers efficiently and provide comfortable transit facilities.

Also Read:- Railways to construct a new line between Chikkamagalur and Hadihalli

- Advertisement -
RELATED ARTICLES

Leave a Reply

- Advertisment -

Most Popular

Discover more from Mysuru Infra Hub

Subscribe now to keep reading and get access to the full archive.

Continue reading