WR Enhances Mumbai Suburban Line Capacity Between Khar and Goregaon

Infrastructure Upgrade Completed Successfully by Western Railway

- Advertisement -

Mumbai- Western Railway (WR) has successfully completed a major infrastructure project on the 8.8 km stretch between Khar and Goregaon, introducing a 6th line. This addition is set to have significant benefits for the Mumbai suburban rail section, including reduced congestion and improved train services’ punctuality.

Also read | First Vande Sadharan Train Rolls Out

Efficient Execution

The project began on October 7, 2023, with a Pre-Traffic Work Order spanning 30 nights, followed by a 29-night Traffic Works Order (TWO), including Non-Interlocking work (NI) for 10 nights at six stations.

- Advertisement -

The work involved laying 12 Turnouts and three Trap points on the existing 5th line and both Fast lines. It also included laying 8 Turnouts on the new 6th line while dismantling nine existing Turnouts and three Trap points from the existing lines. Independent connectivity to both the 5th and 6th lines was provided to Bandra Terminus Yard after slewing 700 meters of existing track and dismantling five points, including a diamond crossing.

The project utilized various heavy machinery such as T-28, UNIMAT, Duomatic, UTV, Hydraulic Cranes, and JCBs to ensure the smooth and efficient execution of the work.

Also read | Indian Railways to Operate “North East Discovery” Train Tour from Delhi

- Advertisement -

Improving Connectivity and Accommodating Growth

The project also involved land acquisition, with both private and government land (BMC) being used. To enhance the alignment, 27 new Foot Over Bridges (FOBs) were constructed in place of existing FOBs that infringed on the alignment. Additionally, existing railway structures that obstructed the project were dismantled, making way for new structures, including 192 flats for Railway Quarters, six Electronic Interlocking (EI) buildings, two Traction Sub Station (TSS) buildings, and three Booking Offices.

In the process, around 607 Project Affected People (PAPs) were rehabilitated and provided with alternate allotments. Furthermore, nearly 1000 trees were relocated and transplanted to preserve the environment.

Also read | Conversion of Vasco Da Gama-Patna Weekly Express Rakes from Conventional to LHB Rake

- Advertisement -

Benefits for Mumbai Suburban Rail

The completion of this project marks a significant enhancement of the line capacity for the Mumbai suburban rail section. With reduced congestion and improved punctuality, this infrastructure upgrade will also pave the way for the addition of more train services, improving the overall commuting experience for passengers.

Also read | Chennai’s Rail Network Gets a Boost: Chennai Beach – Chennai Egmore 4th Line Project Progress

- Advertisement -
RELATED ARTICLES

Leave a Reply

- Advertisment -

Most Popular

Discover more from Mysuru Infra Hub

Subscribe now to keep reading and get access to the full archive.

Continue reading